Windows, Shingles Done!

October 2nd, 2008

They came and installed all the windows today. They also put all the shingles on the roof. They were still there finishing up the 3rd car garage while Beka went to take pictures. Not entirely sure what they are doing tomorrow. They did some more plumbing as well. Looks like they ran some of the mains and hooked into the main in the crawl space. They look like they are primed to pour some more cement but who knows. We will just watch and see.

Posted in House | No Comments »

Plumbing Time!

October 1st, 2008

The framing is all done. Right on time! They were super busy today. The neighbor came over and told Beka that they could barely drive down the street today cuz so much was going on. They finished the roof this morning and then put down the black paper stuff to prep for the shingles. The plumber came today and put in all the plumbing. They also tore out the cracked piece of concrete in our driveway. It’s on the schedule to pour the patio tomorrow, so I would assume they are going to pour the patio, driveway, and the extra piece in the back that they messed up. If you look in the garage you can see the windows stacked in there as well. They are putting those in tomorrow too. We scheduled our Framing meeting for Tuesday to review the framing to see what needs to be fixed before they continue. As far as I can tell there are only a couple 2×4’s that need to be replaced. They also framed in the attic access and cut the hole in the downstairs closet to access the crawl space.

Posted in House | No Comments »

Roof Day 1 & 2

October 1st, 2008

They are just about done with the roof. You can see one little section not done yet. I’m sure they will finish that up tomorrow. The windows are scheduled to be delivered tomorrow as well as a few other things. They should be starting shingles very soon as well. After that the weather can do whatever it wants. I am praying for a warmish summer until we get in, so sorry to the winter lovers.

Posted in House | No Comments »

Tyler’s Train Ride

September 28th, 2008

After dropping Chris off at the airport on Saturday, Tyler and I went for a train ride! We took FrontRunner from Salt Lake to Layton. We ate lunch at Doug and Emmy’s (well, it was breakfast at lunch time, they have the best scones!) and then caught the train back to Salt Lake. He loved it and has been talking about it ever since!

Posted in Tyler | No Comments »

2nd Floor Framing, Day 2

September 28th, 2008

Sorry, the pictures aren’t that great. The sun was setting as we arrived at the house. It is amazing what they can get done in one day! On this day they put up all of the exterior walls and all of the interior ones! The roof is next.

Posted in House | No Comments »

2nd Floor Framing

September 25th, 2008

This is going up quick. If you blink, or miss a day getting on here you miss a lot. Today they installed some rough stairs and put down the second floor. I am heading out of town next week so I will be relying on Beka to update us all. I’m sure she will do great. This sure has been fun going over to the house everyday to see our house go up piece by piece. I was working late tonight and so I went over to the house after dark tonight. I climbed up into where my bedroom will be, and realized that we have un-blocked view to the Mt Timp Temple. It was a spectacular view. We picked a great lot. Unless they build a massive building behind us, we should have a great view for quite some time.

Posted in House | 2 Comments »

1st Floor Framing-Day 2!

September 24th, 2008

Posted in House | No Comments »

1st Floor Framing!

September 23rd, 2008

Today they finished up framing in the crawl space, put down the 1st floor, and have half of the walls up.  As you can see, they need to fix the cement on our back patio.  We wanted it to start where the bay window stopped, not under it!  We are still 2 days ahead of schedule!

Posted in House | No Comments »

Framing Started Ya’ll!

September 22nd, 2008

So I got an e-mail yesterday during church from our sales chick, Tiffany. She informed me that our dates had changed, but for the better. Instead of starting the framing on October 1st, they were going to start on Sept. 24th. A week early! Then today on my way home from work I thought I would stop by and check out the house. They were only suppose to seal the concrete today, but as you can see from the above pictures, they did a little more than seal the concrete. We have wood, and lots of it! They have started framing today and they can’t be stopped. Imagine our suprise to have framing started a week and a half early. You won’t hear any complaining coming from us apt dwellers. I rushed home to get our camera, just to find out that our internet was down for the 80th time in 6 weeks. Lucky for me we have the best realtor in the entire world. Actually she technically isn’t our realtor anymore, but a super friend. She lets me borrow her Air card everytime my internet goes down, which goes down quite often. Anyway, we are super stoked to get this show on the road. Can’t wait to see what they do tomorrow!

Posted in House | No Comments »

Driveway!

September 22nd, 2008

They poured the rest of our concrete on Friday. Driveway, garage, side man door, and back patio. We are moving right along.